Free Spreadsheet

Change request form, cost and time impact

A variation is not just a price. This form makes both parties agree the money and the days before the work starts.

4.9/5 · 127 Client ratings
Updated 19 Sep 2026
✓ Warranty-backed work✓ On-time completion guarantee✓ Design & build under one roof✓ 250+ projects delivered

The form, with a worked variation

CR-004 in full below. Note the third section: most variation forms price the material and forget that the project now takes six days longer.

Change request CR-004 — worked example
DescriptionUnitQtyRateAmount
Additions requested by the client
Convert the second bedroom wardrobe from hinged to slidingsq ft48₹420₹20,160
Add a pull-out pantry unit to the kitchen tall baynos1₹28,500₹28,500
Add profile lighting to the crockery unitrft5₹1,850₹9,250
Upgrade master bedroom shutters from laminate to acrylicsq ft64₹640₹40,960
Add a shoe drawer bank at the entrancesq ft8₹1,650₹13,200
Additions requested by the client — sub-total₹112,070
Omissions agreed in exchange
Omit the study table in the second bedroomrft-4₹7,200₹-28,800
Omit the balcony deckingsq ft-36₹340₹-12,240
Reduce false ceiling in the passage to a plain bandsq ft-22₹125₹-2,750
Omissions agreed in exchange — sub-total₹-43,790
Time and preliminaries impact
Additional site days caused by this variationdays6₹4,200₹25,200
Re-drawing and re-approval of the affected elevationsLS1₹9,500₹9,500
Time and preliminaries impact — sub-total₹34,700
Sub-total (ex-GST)₹102,980
GST @ 18%₹18,536
Grand total (incl. GST)₹121,516

Negative quantities are omissions and net off automatically. The grand total is the net change to the contract value.

How to run variations

  1. One form per variation, numbered. Bundling four changes into one form makes each impossible to price or reverse.
  2. Price the time. Six extra site days on a supervised project is a real cost to both sides, and it is the part that gets argued about later.
  3. Offer omissions against additions. It is the most effective way to keep a variation budget-neutral.
  4. Sign before starting. A variation executed and priced afterwards is a negotiation, not an agreement.

Three arguments it prevents

  • “That change was free.” Nothing is free once the carcass is cut; the form makes the cost visible at the moment of asking.
  • A project that finishes three weeks late with no explanation. Signed time impacts add up to a documented extension.
  • Variations priced at the end, in bulk. By then the client has no leverage and the contractor has no incentive to be modest.

Download the form (XLSX) →

Check the clause that governs this in the contract clauses checklist, and track the money in the budget planner.

Frequently asked questions

How much do variations typically add to a project?+

Five to twelve per cent on a well-specified project and twenty per cent or more where design decisions were left open. The number correlates almost exactly with how complete the drawing set was at contract stage.

Can the contractor refuse a variation?+

Yes, if it is outside their competence, affects a warranty or cannot be done in the remaining programme. A reasonable contractor will price it and state the time impact. A contractor who accepts every variation without a time impact is either not thinking or not telling you.

What rate applies to extra work?+

Whatever was fixed in the contract, in the same units as the BOQ. That is why the extra-work rate belongs in the contract at signature: it is the only moment at which you have any negotiating position on it.

Do omissions get credited at the full rate?+

Usually at the rate less any material already ordered or work already done. If the study table has been manufactured, omitting it saves you the installation only. This is why omissions are worth raising early and are worth almost nothing late.

Should small changes go through the form?+

Anything above roughly Rs 10,000 or anything with a time impact, yes. Below that, keep a running list and settle it in one form at the end. What must not happen is a series of verbal agreements that surface as a single unexplained line in the final account.

Related pages

Start your project

Let's design a space worth coming home to.

Free consultation, transparent pricing, and a team that handles design and execution end to end.

📞 CallFree Quote