Free Spreadsheet

Interior budget planner, committed is the number that matters

Seventeen heads, five money columns and three formulas that tell you where the project is really going.

4.9/5 · 127 Client ratings
Updated 19 Sep 2026
✓ Warranty-backed work✓ On-time completion guarantee✓ Design & build under one roof✓ 250+ projects delivered

The planner, with a worked project

The full sheet is below, with the formulas calculated. The comment column is doing more work than it looks — it is the record of why the variance exists.

Interior budget planner — worked project
HeadBudget (Rs)Committed (Rs)Paid to date (Rs)Balance to pay (Rs)Variance vs budget (Rs)Variance %Comment
Design and drawings90000850008500005000-5.6Fixed fee, closed
Civil and demolition15000020400014000064000-5400036.0Extra wall found to be structural; rerouted
Electrical14000014800010000048000-80005.7Nine extra points added at first fix
Plumbing and waterproofing1600001670001670000-70004.4Ponding test passed, paid in full
False ceiling550005250030000225002500-4.5Under budget, plain design chosen
Flooring and tiling130000118000118000012000-9.2Batch discount on vitrified tile
Painting1100001120006000052000-20001.8Two extra coats on the west wall
Modular kitchen38000034800020000014800032000-8.4Laminate instead of acrylic on wall units
Kitchen hardware5000052000520000-20004.0Tandem drawers upgraded
Countertop25000210002100004000-16.0Quartz, 20 mm
Wardrobes2300002250001200001050005000-2.2Sliding in master, hinged in bedroom 2
Loose joinery17000016200090000720008000-4.7TV, crockery, study, shoe unit
Bathroom fittings1200001410001410000-2100017.5CP brand upgraded by the client
Appliances18000017400017400006000-3.3Hob, chimney, oven, dishwasher
Loose furniture and soft goods2500001180006000058000132000-52.8Sofa and beds ordered; curtains pending
Society, deposits and debris4500052000520000-700015.6Deposit refundable at closeout
Contingency120000000120000-100.0Hold until snag closure

Balance, variance and variance percentage are live formulas. GST is applied at 18 per cent across budget, committed and paid.

How to keep it honest

  1. Enter the commitment on the day you sign, not on the day you pay. That is the entire value of the sheet.
  2. Never revise the budget column to match the spend. Revising the target to hit it is how projects overrun invisibly.
  3. Write the reason in the comment column every time a variance appears. In three months you will not remember.
  4. Move money out of contingency explicitly, with a note, rather than letting it drain.

Three things it reveals early

  • A civil head running 36 per cent over in week four, which is recoverable, rather than in week twelve, which is not.
  • Loose furniture uncommitted at 47 per cent of its budget three weeks before move-in — the classic late scramble.
  • Contingency untouched but already spoken for, which is the difference between a buffer and an illusion.

Download the planner (XLSX) →

Set the starting numbers with the cost estimate format and read hidden costs in interior projects.

Frequently asked questions

Why track committed rather than paid?+

Because paid tells you history and committed tells you the future. A project can be 30 per cent paid and 95 per cent committed, at which point the final cost is already decided. Tracking only payments means you discover an overrun when it is too late to change anything.

What variance is acceptable?+

Plus or minus 5 per cent on a head, and under 8 per cent on the total, on a well-specified new-flat project. Renovations run wider because of what is found behind walls. A head running more than 20 per cent over needs a conversation that week, not at the next milestone.

Should loose furniture be in the same sheet?+

Yes, as its own head. It is typically 15 to 25 per cent of what people actually spend and it is almost always the head that gets squeezed at the end. Having it visible from week one stops the sofa budget quietly funding the kitchen upgrade.

How much contingency should sit in the sheet?+

Seven to twelve per cent of works for a new flat, twelve to fifteen for a renovation. Keep it as a head with a zero committed value at the start. Every release from it should have a dated comment explaining what it paid for.

What are the most common overruns?+

Civil work discovered after demolition, electrical points added at first fix, bathroom fittings upgraded by the client, and site extension costs from delays. Three of those four are client decisions, which is worth knowing before blaming the contractor.