Free Spreadsheet

Work order format, one trade, one package

What a work order to a single trade should contain, worked as a carpentry package for a 3BHK.

4.9/5 · 127 Client ratings
Updated 19 Sep 2026
✓ Warranty-backed work✓ On-time completion guarantee✓ Design & build under one roof✓ 250+ projects delivered

The work order, priced

The full example is below. Note how much of it is not manufacture: handling, site cutting, scaffolding and debris are real costs that get omitted and then argued about.

Carpentry work order — worked 3BHK package
DescriptionUnitQtyRateAmount
Scope — manufacture and install
Wardrobe units as per drawing WD-01 to WD-04, MR ply carcasssq ft196₹1,180₹231,280
Kitchen base and wall units as per drawing KT-01sq ft78₹1,320₹102,960
TV unit and crockery unit as per drawing LV-02sq ft64₹1,240₹79,360
Study and bedside units as per drawing BR-03sq ft34₹1,180₹40,120
Loft units, all roomssq ft58₹940₹54,520
Scope — manufacture and install — sub-total₹508,240
Client-supplied material handling
Fixing of client-supplied hardware, per shutter or drawernos96₹145₹13,920
Fixing of client-supplied laminate, labour onlysq ft430₹95₹40,850
Site storage, protection and stacking of free-issue materialLS1₹18,000₹18,000
Client-supplied material handling — sub-total₹72,770
Site works
On-site cutting, edge banding and touch-upLS1₹42,000₹42,000
Scaffolding, tools and consumablesLS1₹26,000₹26,000
Daily debris clearance to the society collection pointLS1₹15,000₹15,000
Site works — sub-total₹83,000
Sub-total (ex-GST)₹664,010
GST @ 18%₹119,522
Grand total (incl. GST)₹783,532

Measurement basis: elevation area of finished joinery. Free-issue material is recorded separately on a signed receipt note.

How to issue one

  1. Reference drawings by number and revision in every scope line. “As discussed” is not a scope.
  2. Price free-issue handling. If you are supplying laminate or hardware, someone has to receive, store, protect and fix it, and that is labour.
  3. Record free-issue material on a signed material receipt note on the day it lands on site.
  4. State the extra-work rate in the same units as the order, before work starts.

Three disputes it avoids

  • “Scaffolding was not in my price.” Section three prices it, so it either is or it is not.
  • Missing free-issue material. A signed receipt note at delivery makes the custody chain clear.
  • A variation priced at whatever the vendor decides. The unit rate is fixed on the order itself.

Download the format (XLSX) →

For the whole-project view use the BOQ template; for the programme, the project timeline template.

Frequently asked questions

When should I use a work order instead of a full contract?+

When you are appointing a single trade for a defined package — carpentry, painting, electrical — and you or your designer are coordinating between them. A work order is shorter than a contract but it must still carry scope, price, programme, payment and warranty, or it is just an email.

Who takes responsibility when trades are appointed separately?+

You do, or your project manager does. That is the trade-off: separately appointed trades are usually 10 to 20 per cent cheaper than a turnkey contract, and every coordination failure between them is yours to resolve. The saving is real and so is the work.

How is free-issue material handled?+

Recorded on a signed material receipt note the day it arrives, stored at the vendor's risk while on site, and reconciled at completion. Wastage allowance should be agreed in advance — typically 5 per cent for laminate and 10 per cent for tile — or every shortfall becomes an argument.

What retention applies to a single trade?+

Five to ten per cent for 30 days, the same as a main contract. For carpentry specifically, hold it until the shutters have been through one full monsoon cycle if you can; alignment issues from humidity show up in that period.

Should the work order include a programme?+

Yes, with a start date, a duration and the dependency it waits on. A carpentry vendor who does not know that tiling finishes in week nine will either arrive early and stand idle or arrive late and delay everyone downstream.

Related pages

Start your project

Let's design a space worth coming home to.

Free consultation, transparent pricing, and a team that handles design and execution end to end.

📞 CallFree Quote