In BKC the question is not design-build versus traditional. It is who carries the landlord, and on a floor with four nominated vendors that is worth paying for.

4.9/5 · 127 Client ratings
Updated 19 Sep 2026
✓ Warranty-backed work✓ On-time completion guarantee✓ Design & build under one roof✓ 250+ projects delivered

Design-build against the split model

Larger tenants often appoint a design firm, a project management consultancy and a contractor separately. It is a legitimate model and it is slower. Here is where the time actually goes on a BKC floor.

Programme comparison on a BKC office floor
StageSplit modelDesign and buildDifference
Concept to detailed design8 – 10 weeks6 – 8 weeksBuildability resolved during design
Tender and award4 – 6 weeksNot required4 – 6 weeks
Landlord approval of services3 – 5 weeks, after tenderRuns in parallel with design2 – 4 weeks
Nominated vendor orderingAfter awardAt design freeze2 – 3 weeks
Construction14 – 20 weeks14 – 20 weeksNone
Total to occupation29 – 41 weeks22 – 32 weeks4 – 7 weeks earlier

On 9,000 sq ft at prevailing BKC rents plus service charge, five weeks of earlier occupation is worth roughly ₹40–₹55 lakh. That is the honest commercial case for design-build here, and it is larger than any fee difference.

Worked example: 9,000 sq ft chargeable floor, turnkey

BKC turnkey office floor, itemised
Package₹ lakhCovers
Design, documentation and landlord submissions14.5Concept to as-built, all landlord approval packages
Landlord charges, supervision, passes and protection22.8Including night-shift supervision and lift bookings
Furniture, workstations, seating and storage74.082 seats, six meeting rooms, breakout and reception
Ceiling, lighting and controls41.5Daylight dimming on the glazed edge; access panels coordinated
Electrical, UPS, data and containment38.2Dual-source distribution, 1.4 kVA per seat UPS
HVAC, VAV rebalancing and BMS — nominated vendor33.6Passed through at cost, programmed by us
Fire detection and sprinkler modification — nominated vendor27.4Passed through at cost
Partitions, glazed fronts and acoustic doors25.0Boardroom Rw 50, meeting rooms Rw 45
Flooring17.0Carpet tile throughout, stone to the lift lobby
Pantry, wellness room and washroom upgrade8.0Pantry for 82; two focus and wellness rooms
Commissioning, handover and contingency4.0Integrated testing, O&M set, as-built drawings
Total, ex-GST306.0₹3,400 per sq ft on 9,000 sq ft chargeable

Add 18% GST. Nominated vendor packages are ₹61 lakh, 20% of the contract, shown at pass-through cost with the landlord's quotations attached.

One contract across the landlord interface — Greenbox Design Studio
BKC · Turnkey

One contract across the landlord interface

Who carries what risk

Risk allocation on a BKC turnkey contract
RiskWho carries it in our contractHow it is managed
Design does not meet the landlord's manualUsServices concept submitted for comment during design, not after
Nominated vendor is lateShared, with a defined mechanismOrders at design freeze; the landlord is copied on every chase
Night-work slots unavailableUsFirst six weeks of slots booked before contract signature
Crew fails security vettingUsOne fixed crew list lodged well in advance, with reserves vetted
Client changes the layout after freezeYouVariation priced in writing with programme impact stated
Furniture lead timeUsOrdered at design freeze; a stock alternative identified for every long-lead item
Base-build defect discovered on strip-outYou, as a landlord matterDocumented and raised within 48 hours with photographs

Furniture inside the contract

We include furniture in BKC turnkey contracts as a matter of course, and clients occasionally question it. The reason is a handover date. A floor that is built, commissioned and empty is not occupiable, and furniture is the single most common long-lead item on a corporate fit-out — twelve to eighteen weeks on imported task seating, longer on bespoke. Inside the contract it is ordered at design freeze against a programme we control. Outside it, it is ordered when procurement gets to it, and we have watched finished floors sit empty for a month for exactly that reason.

What a BKC turnkey contract must state explicitly

  • Which area basis the rate applies to. Chargeable, usable or carpet. A rate quoted against the wrong one moves the contract value by a fifth.
  • Which packages are pass-through. Nominated vendors listed by name, with the landlord's quotations attached and no margin applied.
  • How much of the labour is night work, at what premium, and what happens if the building withdraws slots.
  • What handover means. Commissioned, tested, furnished, cleaned, with as-built drawings and the O&M set issued — not simply built.
  • Reinstatement. An as-built and a reinstatement schedule handed over at completion, so the end of the lease is a quotation rather than a negotiation.

A contract that says all five of those things is usually two pages longer than the one it replaces and several weeks shorter in dispute. On a BKC floor the ambiguity is never in the joinery specification; it is in the interface with the building, and that is exactly where most fit-out contracts go quiet. We put those five clauses on the first two pages rather than in a schedule, because the people who need to read them are the tenant's real estate and finance teams, not their lawyers.

₹2,400Entry rate per sq ft
4–7 wksSaved against the split model
20%Nominated vendor pass-through
22–32 wksDesign to occupation

For the district see interior designers in BKC; for the design side see office interior designers in BKC. Our contract structure is on turnkey interior contractors in Mumbai and the contracting detail on office fit-out contractors.

BKC office floor
BKC workstations
BKC boardroom
BKC glazed meeting rooms
BKC reception

Design-and-build delivery by Greenbox Design Studio.

Frequently asked questions

Is design-build actually faster than appointing a designer and a contractor separately?+

By four to seven weeks on a typical BKC floor. The saving is not in construction, which takes the same time either way. It is in removing the tender and award cycle, running landlord approval in parallel with design rather than after it, and placing the nominated-vendor orders at design freeze. At BKC occupancy costs, five weeks is worth ₹40–₹55 lakh on 9,000 sq ft.

How are nominated vendor costs handled in a turnkey contract?+

Passed through at cost, with the landlord's own quotations attached to our BOQ so you can see exactly what they charged. We add no margin on them. What we do add is programme management — placing the orders at design freeze, chasing with the landlord copied, and holding them to a date — which is where the value actually is.

Should furniture be inside the contract?+

We think so, and we include it. Furniture is usually the longest lead item on a corporate fit-out, and a built, commissioned, empty floor is not a handover. Inside the contract it is ordered at design freeze against a programme we control. Clients who procure it separately frequently occupy two to four weeks later than they needed to.

What happens if the landlord rejects part of our design?+

That risk sits with us, which is why we submit the services concept for landlord comment during design rather than after it. By the time the detailed drawings are issued the landlord has already commented on the ceiling coordination, the sprinkler layout, the BMS interface and the signage. Rejections at the formal stage are then rare and minor.

Can you work on an occupied floor or a phased move?+

Yes, and in BKC it is common where a tenant is expanding into an adjacent demise or refurbishing in place. It means a phased programme with temporary partitions, dust and noise control to an occupied standard, and a larger share of the work in the night window. Budget 12–18% above a vacant-floor equivalent and expect the programme to be about a third longer.