Free Spreadsheet

Snag list template, with status that updates itself

Sixteen worked snags across a 2BHK, with the columns that make a defect list actionable rather than decorative.

4.9/5 · 127 Client ratings
Updated 19 Sep 2026
✓ Warranty-backed work✓ On-time completion guarantee✓ Design & build under one roof✓ 250+ projects delivered

The template, with worked entries

The example log is below. Delete the rows and use the structure, or keep them as a guide to how specific a defect description needs to be.

Snag list template — sixteen worked entries
IDRoomElementDefect observedSeverityResponsibilityPhoto refRaisedTargetClosed onStatusRectification cost (Rs)
S-01LivingTV unitLeft drawer fouls the side panel at full extensionMajorCarpentryIMG_104212-Sep16-Sep16-SepClosed0
S-02LivingFalse ceilingCove shadow gap uneven, 8 mm to 18 mm along the dining edgeMajorCeilingIMG_104412-Sep17-SepOpen4200
S-03LivingPaintRoller marks visible on the south wall in evening lightMinorPaintingIMG_104712-Sep18-SepOpen3500
S-04KitchenCounterChip at the sink cut-out, 12 mm, front edgeMajorStoneIMG_105112-Sep19-SepOpen6800
S-05KitchenBase unitBottle pull-out rubs the adjacent shutterMinorHardwareIMG_105312-Sep16-Sep15-SepClosed0
S-06KitchenBacksplashGrout line cracked above the hobMinorTilingIMG_105513-Sep18-SepOpen1800
S-07Master bedWardrobeSliding shutter jumps at the mid-point of the trackCriticalHardwareIMG_106113-Sep15-SepOpen9500
S-08Master bedBedsideSoft-close not engaging on the right drawerMinorHardwareIMG_106313-Sep17-Sep17-SepClosed0
S-09Master bathShowerWater ponds 40 mm from the trap after two minutesCriticalPlumbingIMG_106813-Sep16-SepOpen14500
S-10Master bathVanityMirror cabinet not level, 6 mm across the widthMinorCarpentryIMG_107013-Sep18-SepOpen900
S-11Bedroom 2WardrobeLoft shutter binds against the false ceiling dropMajorCarpentryIMG_107414-Sep19-SepOpen5600
S-12Bedroom 2ElectricalBedside socket dead on the left sideMajorElectricalIMG_107614-Sep15-Sep15-SepClosed0
S-13Common bathWCFlush plate loose in the wall recessMinorPlumbingIMG_107914-Sep17-SepOpen1200
S-14PassageFlooringThree tiles hollow on tapping near the DBMajorTilingIMG_108214-Sep20-SepOpen7400
S-15BalconyPaintEfflorescence patch below the chhajja dripMajorPaintingIMG_108514-Sep21-SepOpen5200
S-16Whole flatCleaningProtective film left on 11 handles and two glass panelsMinorSiteIMG_108814-Sep15-Sep15-SepClosed0

The Status column is a formula: =IF(closed date is blank, "Open", "Closed"). The cost column totals with an 18 per cent GST row beneath.

How to run a snag list

  1. Describe the defect, do not name it. “Drawer fouls the side panel at full extension” is actionable; “drawer problem” is not.
  2. Photograph everything and reference the file name. Sixteen photographs settle sixteen conversations.
  3. Grade severity honestly. Marking everything Critical is how a list stops being read.
  4. Send it once, as one document. A consolidated list gets scheduled; a stream of messages gets triaged and forgotten.

Three things it fixes

  • Snags raised verbally and forgotten. A dated row with a responsible trade survives a change of site supervisor.
  • A final payment released against a promise. The cost column tells you what the open items are worth.
  • Arguments about whether an item was ever raised. The Raised date column ends them.

Download the template (XLSX) →

Use it alongside the handover checklist and the snag list and handover guide.

Frequently asked questions

How many snags are normal on a 2BHK?+

Twenty to forty on a well-run project, of which most are Minor. A list of five usually means the walk was not thorough. A list of a hundred and twenty usually means the finishing trades left early. What matters is the Critical and Major count, which should be in single figures.

Who fills in the rectification cost?+

You do, as an estimate of what the item would cost to fix if the contractor walked away. It is not a charge and you are not invoicing for it. It exists so that when you hold back money against open items, the amount is proportionate and defensible.

What is the difference between Critical, Major and Minor?+

Critical means the flat cannot be used safely or a defect will worsen — water ponding, a dead circuit, a sliding shutter that jumps. Major means the item does not perform as specified. Minor means cosmetic. Sequence the rectification in that order rather than room by room.

When should the snag walk happen?+

Two walks. The first in the last week of the programme, with the contractor present, in daylight and again after dark. The second after 30 days of occupancy, before you release retention. The second walk reliably finds items the first could not, because nothing had been used yet.

Can I use this for a commercial fit-out?+

Yes, but snag by zone rather than by room and add a column for the system involved — HVAC, electrical, access control, AV. On a fit-out the walk should happen zone by zone as each is completed, not as a single exercise at the end.