Office move planning template, lease to first working day — Greenbox Design Studio
Free Spreadsheet

Office move planning template, lease to first working day

Twenty-one tasks across six workstreams, with the one line most move plans forget still on it.

4.9/5 · 127 Client ratings
Updated 19 Sep 2026
✓ Warranty-backed work✓ On-time completion guarantee✓ Design & build under one roof✓ 250+ projects delivered

The move plan in full

All 21 tasks below, with finish weeks calculated. Read the last two rows before you read the rest.

Office move plan — 16-week worked example
WorkstreamTaskOwnerStart weekDuration (wks)Finish weekStatusBudget (Rs)
PropertyLease signed, fit-out manual received and readAdmin lead111Done0
PropertyLandlord drawing submission and approvalDesign234Done0
PropertyFit-out deposit, insurance and contractor indemnity lodgedFinance212Done350000
DesignBase build survey and measured drawingsDesign111Done60000
DesignTest fit, headcount plan and department adjacencyDesign223Done145000
DesignReflected ceiling plan and MEP coordinationDesign425In progress120000
Fit-outPartitions, glazing and ceilingContractor649Not started2850000
Fit-outElectrical, data and lighting installationContractor7410Not started1940000
Fit-outHVAC modification, balancing and commissioningMEP8310Not started1260000
Fit-outFlooring, painting and joineryContractor10312Not started1480000
StatutoryFire NOC coordination and detector relocation sign-offConsultant9311Not started185000
ITRack, patching, switch install and Wi-Fi surveyIT12213Not started960000
ITCircuit provisioning and cutover rehearsalIT13214Not started240000
FurnitureWorkstation and chair order placed against the approved planAdmin lead616Not started2150000
FurnitureDelivery, build and cleaningVendor13214Not started0
MoveAsset tagging and crate allocation at the old officeAdmin lead14114Not started85000
MoveBuilding permissions, lift booking and security passesAdmin lead14114Not started45000
MovePhysical move over a weekend, IT last out and first inVendor15115Not started320000
PeopleFloor plan, seating allocation and induction communicationHR14215Not started0
CloseoutSnagging, O&M handover and defects register openedDesign16116Not started0
CloseoutOld premises reinstatement and deposit recoveryAdmin lead16217Not started480000

Finish week is a live formula. Budget totals carry an 18 per cent GST row and a grand total.

How to run the plan

  1. Assign a single owner per task. Shared ownership on a move plan means nobody chases the landlord in week three.
  2. Submit landlord drawings in week two. Approval turnaround is outside your control and is the most common source of slippage.
  3. Rehearse the IT cutover. One week 13 rehearsal is worth more than any amount of week 15 planning.
  4. Budget reinstatement of the old premises from day one. It is due at lease end whether or not anyone planned for it.

Three things that derail office moves

  • Landlord approval treated as a formality. It is a three-week line item on most Mumbai buildings.
  • Furniture ordered late. Lead times of six to eight weeks mean the order belongs in week six, not week twelve.
  • Reinstatement discovered at handback. Rs 180 to 420 per sq ft, payable, unbudgeted.

Download the template (XLSX) →

Pair it with the office fit-out checklist and see rates on the office cost page.

Frequently asked questions

How long does an office move take to plan?+

Sixteen weeks from lease signature to first working day for a mid-size floor, of which ten to fourteen are the fit-out. Compressing below twelve weeks is possible only with a warm shell, fast landlord approval and furniture ordered before the design is finished, which carries its own risks.

Who should own the move plan?+

One named person on the tenant side, usually an admin or facilities lead, with the design and fit-out lines owned by the contractor. Splitting overall ownership between IT and admin is the most common way a move loses a fortnight in the middle.

When should furniture be ordered?+

Week six, against the approved test fit, because lead times run six to eight weeks for most commercial furniture in India and longer for imported chairs. Ordering in week twelve means furniture arriving after the IT migration, which is the wrong order.

What is an IT cutover rehearsal?+

A dry run of the circuit switchover, patching and critical-system access at the new floor, done a week before the move with a small group. It finds the DNS entry nobody updated and the printer that was never mapped, at a point where fixing it is an afternoon rather than a crisis.

What does reinstatement cost?+

Rs 180 to 420 per sq ft in Mumbai, depending on how much of the fit-out has to come out. Read the obligation in your old lease before you plan the move budget. On a 5,000 sq ft floor it can be Rs 10 to 20 lakh, which is not a rounding error.