Sleepmax — The Boardroom — Greenbox Design Studio
Case Study · Commercial

Sleepmax — The Boardroom

Fourteen seats, one marble table that had to arrive in a goods lift, and a wall of glass that had to sound like a solid one.

4.9/5 · 127 Client ratings
Updated 19 Sep 2026
✓ Warranty-backed work✓ On-time completion guarantee✓ Design & build under one roof✓ 250+ projects delivered
420 sq ftRoom area
14Seats
48 dBPartition rating
5 weeksZone programme

This is one room of a larger project. The full programme, the four-zone strategy and the reason the client lost no trading days are covered on the parent case study: Sleepmax corporate office fit-out. This page covers only what was specific to the boardroom.

The brief for this room

A boardroom on an open floor plate has two jobs that pull against each other. It has to feel connected to the business — glass, daylight, visible activity — and it has to be genuinely confidential, because the conversations that happen in it are the reason it exists. Most offices resolve that by building a glass box and then discovering you can hear it from the corridor.

  • 420 sq ft, 24 ft × 17 ft 6 in, on the internal edge of the floor plate.
  • Fourteen seats at a single table, with room to walk behind a seated person on both long sides.
  • Full video-conference capability — an 85 in display, ceiling microphones, a horizon camera.
  • Speech privacy from the adjacent corridor and the open workspace beyond it.
  • Built as zone three, with zones one and two already handed back and occupied.

The constraints

Boardroom constraints and the decisions they forced
ConstraintWhat it ruled outWhat we did instead
Occupied adjacent zonesDaytime demolition and core drillingAll noisy scope in after-hours windows, with sealed dust barriers to the live zones
Goods lift car 1,100 × 2,000 mmA single-piece 14-seat table topMarble table in three slabs with concealed mechanical joints, sized to the lift car
Glass partitions on two sidesMeeting the acoustic brief with single glazing48 dB double-glazed system, full height to slab, with acoustic seals at head and base
Confidentiality plus daylightSolid walls or permanent frostingSwitchable privacy film on both glazed elevations, controlled from the room
Hard surfaces — glass, stone, displayAn untreated ceilingAcoustic raft over the table plus carpet tile, taking reverberation to about 0.5 seconds
Design and build under one accountable roof — Greenbox Design Studio
Case Study · Commercial

Design and build under one accountable roof

What we did

  1. Take the partitions to the slabAcoustic performance in a glass meeting room is decided above the ceiling, not below it. Partitions run full height to the structural slab with an acoustically sealed head detail. A 48 dB partition that stops at the ceiling grid performs like a 30 dB one.
  2. Specify the table to the lift, then to the designThe goods lift car set the maximum slab dimension. The table is three marble sections on a concealed steel substructure with mechanical joints tightened from below — the joint lines fall on the seating rhythm so they read as deliberate.
  3. Use switchable film instead of blindsBlinds in a boardroom collect dust, break, and always end up half-raised. Switchable privacy film goes from clear to opaque on a wall switch with no moving parts and no fabric.
  4. Put the acoustic work in the ceilingA suspended acoustic raft directly over the table absorbs the first ceiling reflection, which is the one that most degrades speech intelligibility for the people at the far end. The rest of the ceiling stays as an accessible grid for sprinkler and detector access.
  5. Integrate the AV before the ceiling closedDisplay position, ceiling microphone array, camera height and cable routes were all fixed before the ceiling design was finalised — the same sequencing rule that governed the whole project.
  6. Power and data in the tableA flush cable management spine down the table centre with power, HDMI and data at four positions, fed through the steel substructure and a floor box, so no cable is visible above the surface.
Sleepmax boardroom with a marble table, integrated display and acoustic ceiling raft, Mumbai
The boardroom — three-section marble table, 48 dB glazed partitions, acoustic raft over the table

Materials and specification

Boardroom specification
ElementSpecificationReasoning
PartitionsDouble-glazed 12 mm + 12 mm laminated, 48 dB rated, full height to slab, aluminium framingThe only reliable way to get confidentiality out of a glass room
PrivacySwitchable PDLC film on both glazed elevations, wall-switchedNo fabric, no dust, no mechanism; instant and total
TableThree-section marble top on a concealed powder-coated steel substructure, mechanical jointsSized to the 1,100 × 2,000 mm goods-lift car; joints aligned to the seating rhythm
CeilingAccessible 600 × 600 grid with a suspended acoustic raft over the tableAbsorption where it matters, sprinkler and detector access everywhere else
FlooringCarpet tile over levelled screed, acoustic underlayFootfall isolation and broadband absorption in a room full of hard surfaces
Wall finishTimber-veneer panelling to the display wall, acoustic fabric to the rear wallThe rear wall is the reflective surface behind the camera and the microphone array
AV85 in display, ceiling microphone array, horizon camera, in-table connectivity spinePositions fixed before the ceiling was designed, not after
LightingDimmable 4000 K linear over the table, 3000 K perimeter, separate display sceneA single bright scene washes the display and flattens faces on camera

Programme — zone three

Five-week boardroom programme within the four-phase project
StageDurationNotes
Demolition and partition framingWeek 1, after hoursSealed dust barriers to the occupied zones on both sides
Services and AV first fixWeek 2HVAC branch, electrical, data, microphone and camera cabling before any ceiling
Glazing and ceilingWeek 3Partitions glazed and sealed at head and base, acoustic raft hung, grid closed
Table, joinery and finishesWeek 4Marble sections lifted in on booked slots, substructure levelled, joints closed and polished
AV commissioning and handoverWeek 5Microphone gain structure set, camera framing, lighting scenes, snag closed, zone handed back

The outcome

Speech from inside the boardroom is not intelligible in the adjacent corridor at normal conference volume, which is the practical test that matters and the one a partial-height partition fails. Reverberation inside sits at roughly 0.5 seconds, so the far end of a video call hears the person at the far end of the table.

The table arrived in three pieces on three lift slots and was assembled in the room in a single afternoon. Nothing was stranded in the loading bay, which on a Mumbai commercial project is not a small claim.

The acoustic glass was the line item we questioned hardest and it is the one we would keep first if we did it again.

Facilities Manager, Sleepmax

What we would highlight

  1. Acoustic partitions must run to the slab. Stopping at the ceiling grid wastes the entire rating you paid for.
  2. Size stone to the lift before you size it to the room. A slab that cannot go up is a total loss, not a delay.
  3. Switchable film outlasts blinds. No fabric to collect dust, no mechanism to jam, no half-raised blind in a client meeting.
  4. Treat the ceiling over the table. The first ceiling reflection is what makes the far end of a long table unintelligible on a call.
  5. Fix AV positions before the ceiling design. Reversing that order is how microphones end up wherever there was space.
Greenbox commercial interior project in Mumbai — 1
Greenbox commercial interior project in Mumbai — 2
Greenbox commercial interior project in Mumbai — 3
Greenbox commercial interior project in Mumbai — 4
Greenbox commercial interior project in Mumbai — 5

Selected work by Greenbox Design Studio. Tap any image to enlarge.

Frequently asked questions

How do you make a glass boardroom confidential?+

Double-glazed acoustic partitions rated around 48 dB, run full height to the structural slab with sealed head and base details. Most glass meeting rooms fail because the partition stops at the ceiling grid and sound travels over it through the ceiling void — a 48 dB system installed that way performs closer to 30 dB.

Is switchable privacy film better than blinds in a meeting room?+

In our experience yes. It goes clear to opaque instantly on a wall switch, has no fabric to collect dust, no mechanism to jam and no half-raised state. It costs more than blinds up front and less over a five-year occupancy, and it is the detail clients comment on most.

How do you get a large boardroom table into a Mumbai office?+

By sizing it to the goods-lift car before approaching the supplier. This table is three marble sections on a concealed steel substructure with mechanical joints tightened from below, each section within the 1,100 × 2,000 mm lift car. The joint lines are aligned to the seating rhythm so they read as intentional.

What makes a boardroom sound bad on video calls?+

An untreated ceiling over a hard table. The first ceiling reflection arrives at the microphone array milliseconds behind the direct voice and smears speech from the far end of the table. A suspended acoustic raft over the table plus carpet tile brought this room to about 0.5 seconds of reverberation.

Can a boardroom be built while the office is occupied?+

Yes. This one was zone three of a four-phase fit-out with zones one and two already handed back and in use. Demolition and core drilling ran after hours behind sealed dust barriers, and quiet trades ran during business hours. The wider approach is described on the Sleepmax office case study.